V-E 2 Site power distributor

Distribution end distributor cabinet (V-E 2)

  • Entrance
    M63 cable entry with strain relief up to max. 50 mm2

    Fuse protection Connection:
    1× miniature circuit breaker 3P 63 A with thermal-magnetic release with frame terminals 10-50 mm2

  • Output
    1x CEE socket 400 V, 32 A, 5-pin
    2x CEE sockets 400 V, 16 A, 5-pin
    6x 230 V, 16 A socket outlets with earthing contact
  • Fuse protection outputs
    1x RCD 63 A, 4-pole, 30 mA, type B all-current sensitive
    1x RCD 40 A, 4-pole, 30 mA, type A, positive current sensitive
    1x LS C 32 A, 3-pole
    2x LS C 16 A, 3-pole
    6x LS C 16 A, 1-pole
  • Site power distributor in sturdy steel cabinet with heavy metal-free plastic coating in blue
  • Lockable single door with spring latch bolt for padlock and recessed handle
  • With side transport handles, two crane eyes at the top, strain relief rail, fastening lugs for ground pegs and earthing screw
  • IP44: with door closed, IP21: with door open

Opis

DIN VDE 0100-704 Standard amendment 2018:

From 2020, the new standard must be met at the start of the construction site or if the power distribution is changed during the construction site period.
On 18 May 2021 the version of the old standard ends, i.e. until then all distributors must be replaced become.
All our site power distribution boards comply with the DIN VDE 0100-704 user standard, so you are on the safe side.

Versions

Distribution end distributor cabinet PU Item no.
V-E 2 44 kVA 1 61842

Details

Security

tested according to
DIN EN 61439
Compliant with DIN VDE 0100-704

[1081][1085]
Technical data

44 kVA

[DE]
Use
[1][2][3]

DIN VDE 0100-704 Amendment to standard 2018Are you up to date?

From 2020, the new standard must be complied with at the start of the construction site or if the power distribution is changed during the construction site period. All our construction site power distribution boards comply with the DIN VDE 0100-704 user standard, so you are on the safe side.

Section no. 704.531.3 says:
" Three-phase sockets up to and including 63A must be protected with a type B residual current device (RCD) in accordance with EN 62423."

Section no. 704.537.101 also states:
"Permanently connected building site power distributors with sockets must contain devices for disconnecting the power supply that can be locked against switching on and can be used by laypersons. A lockable enclosure is not sufficient."

The version of the old standard ends on 18 May 2021, i.e. all distributors must be replaced by then.

More Products